Title: | Timeline: Rose Bowl renovations |
Subtitle: | |
Date: | 2013-02-09 |
Summary: | <b>February 9, 2013</b> - The Pasadena Sun feature the timeline for the Rose Bowl renovations. |
Author: | Joe Piasecki, joe.piasecki@latimes.com |
Publication: | Pasadena Sun |
Content: | Rose Bowl General Manager Darryl Dunn talks about the finished renovations and some that are ongoing at the Rose Bowl in Pasadena. (Raul Roa/Staff Photographer / February 7, 2013) Pasadena might ax Rose Bowl nonprofit Oct. 11, 2010: City Council approves Rose Bowl renovations that are expected to cost $151.9 million. Jan. 25, 2011: Project breaks ground. April 2011: Unanticipated foundation work increases project’s price tag to $156.5 million. December 2011: Cost estimate climbs to $160.7 million after contracts for press box and seating pavilion work come in over budget. January 2012: Press box and seating area demolition work begins. June 2012: Workers finish placing steel beams for press box and seating construction; projected cost of work approved in 2010 reaches $176.9 million. September 2012: Stadium officials approve a $6-million change order for pavilion work that increases the project budget to about $184 million. November 2012: Estimated cost of completing renovation plans reaches $194.8 million. Rose Bowl officials postpone many upgrades planned for 2013 after bids for construction work exceed projections. January 2013: Stadium officials have committed to more than $160 million in construction contracts with about $135 million to pay for them. Pasadena City Council members approve $30 million in additional borrowing so the stadium can pay its bills. 2014 to 2018: Stadium revenue is expected to pay for $16 million in work, increasing total renovation spending to $181 million in 2018. About $14 million in planned upgrades are on indefinite hold pending additional funds. Source: Rose Bowl Operating Co. and City of Pasadena documents -- Follow Joe Piasecki on Twitter: @JoePiasecki. |
Url: | http://www.pasadenasun.com/news/pasadena-0209-timeline-rose-bowl-renovations,0,1906784.story |