ALTADENA -- Nearly half the promises traded for permission
to build a gated community in the Altadena foothills remain
unfulfilled, according to a county audit.
Of the 91 key conditions identified
in the report, 46 are partially finished or incomplete. Most
relate to the developers' failure to build hiking and horse
trails near the La Vina development at the top of Lincoln
Avenue. Street changes meant to improve traffic circulation
and additions planned for nearby Loma Alta Park also remain
incomplete.
Responsibility for the negligence
lies with the developers and with ineffective county
departments that offered little oversight, the report said.
"There's no excuse for the
failures to fully complete the conditions,' said Supervisor
Mike Antonovich, who represents unincorporated Altadena.
"I was outraged by the
findings of the audit,' Antonovich said.
But the report's findings, released
Tuesday, hold little surprise for some Altadena residents.
Many have complained for more than five years that the La
Vina development blocked access to their favorite riding
trails.
Local equestrians held a rally in
January at Loma Alta Park to draw attention to poor trail
conditions.
"Parts of trails just don't
exist anymore. They're gone. They're grown over,' Tracy
Sullivan of Altadena Equestrian Resources said at the event.
After the demonstration, Antonovich
gave county employees 15 days to complete the La Vina audit,
but searching the county's voluminous files instead took
several months.
The 272-home La Vina development
covers 220 acres bordering the Angeles National Forest. The
last phase of 25 houses is nearly complete.
The county first approved the
project in 1989, but legal challenges by opposition group
Friends of La Vina delayed construction until 1996.
Several developers were involved in
La Vina, where some homes now sell for more than $1 million.
The group includes original developers Cantwell/Anderson
Inc. and Southwest Diversified, as well as builders
Brookfield Homes, Compass Homes/La Vina Estates LLC and
Lehman Ali La Vina LLC.
Naming which company must complete
the conditions will take another month. A report identifying
who is responsible is due Nov. 15, along with a completion
time line.
Existing construction bonds should
be sufficient to finish the improvements, said Conal
McNamara, Antonovich's land- use deputy.
The county predicts it will take
one to two years to meet all the requirements.
The audit initially identified more
than 700 conditions, nearly 200 of which fall into
"quality-of-life' categories directly affecting
Altadena residents. Those were narrowed down to 91
"key' requirements.
Promises outside of formal
conditions approved or required by the county were excluded,
such as commitments to establish an economic development
program in Altadena and plant a large oak grove honoring
Gabrielino Indians.
Antonovich said he intends to
ensure there are no repeats of La Vina by revamping how the
county oversees such developments.
The county Board of Supervisors
will vote Tuesday on his motion to restructure the county's
land development process.
-- Becky Oskin can be reached at
(626) 578-6300, Ext. 4451, or by e- mail at becky.oskin@sgvn.com
.